Dept. of Trans. PROGRESS Serial No. Contract No. 15-294-11-31 04-4A3424 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 96% Location: Federal Project: 04-ALA-24-5.6 HSNH-X001(586) 04-ALA-580-20.7 04-ALA-580-44.7 Progress payment No. 004 Payment period ending: 10-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 547,111.00 0.00 2. a. Extra Work 30,758.49 10,553.49 b. Adustment Comp. 9,131.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 587,001.03 10,553.49 5. Mobilization 51,000.00 0.00 6. Total Work Completed 638,001.03 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 636,001.03 8,553.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,553.49