Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-13-51 04-4A5314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 8% 04-ALA-580-0.0/30.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-20-08 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,921.25 78,921.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 78,921.25 78,921.25 5. Mobilization 45,000.00 45,000.00 6. Total Work Completed 123,921.25 7. Deductions 8. a.Contract Retentions -7,892.13 -7,892.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 116,029.12 116,029.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,029.12