Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-09-07 04-4A5334 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 15% 04-MRN-101-0.0/27.6 Federal Project: 04-SON-101-0.0/R56.2 NONE Progress payment No. 01 Payment period ending: 07-20-08 STEINY AND COMPANY INC 27 SHERIDAN STREET VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 260,686.00 260,686.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 260,686.00 260,686.00 5. Mobilization 7,000.00 7,000.00 6. Total Work Completed 267,686.00 7. Deductions 8. a.Contract Retentions -26,068.60 -26,068.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 241,617.40 241,617.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 241,617.40