Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-09-58 04-4A5344 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 53% 04-SOL-80-0.0/R44.7 Federal Project: 04-NAP-80-6.8/8.0 NONE Progress payment No. 03 Payment period ending: 10-20-08 ROSENDIN ELECTRIC INC P O BOX 49070 SAN JOSE CA 951619070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 230,339.00 129,555.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 230,339.00 129,555.75 5. Mobilization 59,075.25 19,691.75 6. Total Work Completed 289,414.25 7. Deductions 8. a.Contract Retentions -23,033.90 -12,955.57 b. Unsatisfactory Prog. -0.01 -0.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 266,380.34 136,291.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,291.92