Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-10-53 04-4A6304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 73% 04-VAR Federal Project: STP-000C(363) Progress payment No. 02 Payment period ending: 06-20-14 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 740,473.50 549,750.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -47,785.96 4. Earned Subject to Retention 740,473.50 501,964.54 5. Mobilization 131,400.00 32,850.00 6. Total Work Completed 871,873.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 871,873.50 534,814.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 534,814.54