Dept. of Trans. PROGRESS Serial No. Contract No. 18-138-09-08 04-4A6704 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 75% Location: Federal Project: 04-VAR NONE Progress payment No. 005 Payment period ending: 05-20-18 AMERICA PACIFIC CONSTRUCTION 7161 CITRUS VALLEY AVENUE EASTVALE CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 124,035.00 4,550.00 2. a. Extra Work 19,912.86 19,912.86 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 143,947.86 24,462.86 5. Mobilization 20,000.00 0.00 6. Total Work Completed 163,947.86 7. Deductions -118.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 163,829.86 24,462.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,462.86