Dept. of Trans. PROGRESS Serial No. Contract No. 16-231-14-35 04-4A8824 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 82% Location: Federal Project: 04-SON-128-17.1/24.7 NONE Progress payment No. 048 Payment period ending: 08-20-16 FIELDSTONE CONSTRUCTION COMPANY 5915 FAUGHT RD SANTA ROSA CA 95403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 162,064.50 840.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 162,064.50 840.00 5. Mobilization 36,922.50 0.00 6. Total Work Completed 198,987.00 7. Deductions -15,255.60 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 183,731.40 840.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 840.00