Dept. of Trans. PROGRESS Serial No. Contract No. 15-141-10-26 04-4A9254 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 99% Location: Federal Project: 04-SM-101-0.0/6.0 NONE 04-SM-82-0.0/4.8 04-SM-84-24.7/28.2 Progress payment No. 016 Payment period ending: 05-20-15 ROADWAY ENGINEERING WORKS INC 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,099,438.05 0.00 2. a. Extra Work 44,636.12 19,511.96 b. Adustment Comp. 687,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,831,574.17 19,511.96 5. Mobilization 260,000.00 0.00 6. Total Work Completed 5,091,574.17 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,071,574.17 19,511.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,511.96