Dept. of Trans. PROGRESS Serial No. Contract No. 20-099-06-40 04-4AA504 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 51% Location: Federal Project: 04-ALA-80-5.9/5.9 NONE Progress payment No. 002 Payment period ending: 04-03-20 BAY LINE CUTTING & CORING INC 501 CESAR CHAVEZ #101B SAN FRANCISCO CA 94124 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 68,972.20 34,974.10 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 68,972.20 34,974.10 5. Mobilization 6. Total Work Completed 68,972.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 68,972.20 34,974.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,974.10