Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-09-09 04-4C0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 70% 04-SOL-80-R26.5/R26.8 Federal Project: NONE Progress payment No. 08 Payment period ending: 09-20-07 PROVEN MANAGEMENT INC 706 SANSOME STREET SAN FRANCISCO CA 94111 Escrow No. 02283 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,045,167.25 184,701.00 2.a. Extra Work 34,299.47 34,299.47 b. Adjustment Comp. 3. Materials on Hand 28,000.00 4,000.00 4. Earned Subject to Retention 4,107,466.72 223,000.47 5. Mobilization 62,542.00 0.00 6. Total Work Completed 4,142,008.72 7. Deductions 8. a.Contract Retentions -205,373.34 -11,150.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,964,635.38 211,850.44 10. Reduction Amt to Escrow 11. Payment to Escrow 205,370.00 12. Net Pymt. this Estimate 211,850.44