Dept. of Trans. PROGRESS Serial No. Contract No. 09-111-08-38 04-4C1524 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 50% 04-SOL-80-20.1/30.6 Federal Project: ACIM-080-2(353) Progress payment No. 11 Payment period ending: 04-20-09 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,030,073.66 195,785.60 2.a. Extra Work 975,816.40 168,273.36 b. Adjustment Comp. 1,326,366.97 84,879.10 3. Materials on Hand 244,759.00 -0.90 4. Earned Subject to Retention 24,577,016.03 448,937.16 5. Mobilization 2,251,000.00 0.00 6. Total Work Completed 26,583,257.03 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,828,016.03 448,937.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 448,937.16