Dept. of Trans. PROGRESS Serial No. Contract No. 23-293-16-43 04-4G0804 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 37% Location: Federal Project: 04-SOL-80-R10.4/30.2 ACIM-802(375) Progress payment No. 022 Payment period ending: 10-20-23 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,328,987.19 4,562,409.92 2. a. Extra Work 4,267,521.10 236,470.04 b. Adustment Comp. 4,768,323.34 258,845.84 3. Materials on Hand 4,962,141.00 -346,869.00 4. Earned Subject to Retention 71,326,972.63 4,710,856.80 5. Mobilization 11,400,000.00 570,000.00 6. Total Work Completed 77,764,831.63 7. Deductions -8,504.92 -500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 82,718,467.71 5,280,356.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,280,356.80