Dept. of Trans. PROGRESS Serial No. Contract No. 25-017-17-10 04-4G0804 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 68% Location: Federal Project: 04-SOL-80-R10.4/30.2 ACIM-802(375) Progress payment No. 041 Payment period ending: 01-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 114,539,748.24 2,290,246.54 2. a. Extra Work 10,524,772.12 114,205.81 b. Adustment Comp. 6,685,535.40 -17,631.60 3. Materials on Hand 1,427,872.00 -657,178.00 4. Earned Subject to Retention 133,177,927.76 1,729,642.75 5. Mobilization 11,400,000.00 0.00 6. Total Work Completed 143,150,055.76 7. Deductions -30,504.92 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 144,547,422.84 1,729,642.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,729,642.75