Dept. of Trans. PROGRESS Serial No. Contract No. 25-052-15-18 04-4G0804 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 70% Location: Federal Project: 04-SOL-80-R10.4/30.2 ACIM-802(375) Progress payment No. 042 Payment period ending: 02-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 116,274,254.52 1,734,506.28 2. a. Extra Work 10,934,500.11 409,727.99 b. Adustment Comp. 6,793,807.64 108,272.24 3. Materials on Hand 391,250.00 -1,036,622.00 4. Earned Subject to Retention 134,393,812.27 1,215,884.51 5. Mobilization 11,400,000.00 0.00 6. Total Work Completed 145,402,562.27 7. Deductions -30,504.92 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 145,763,307.35 1,215,884.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,215,884.51