Dept. of Trans. PROGRESS Serial No. Contract No. 18-141-14-21 04-4G2204 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 18% Location: Federal Project: 04-SON-12-17.7/18.2 SNHG-P012(124) Progress payment No. 003 Payment period ending: 05-20-18 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 643,136.50 525,206.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 16,724.00 16,724.00 4. Earned Subject to Retention 659,860.50 541,930.50 5. Mobilization 329,250.00 329,250.00 6. Total Work Completed 972,386.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 989,110.50 871,180.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 871,180.50