Dept. of Trans. PROGRESS Serial No. Contract No. 19-053-10-30 04-4G2204 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 80% Location: Federal Project: 04-SON-12-17.7/18.2 SNHG-P012(124) Progress payment No. 013 Payment period ending: 02-20-19 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,558,069.90 220,258.70 2. a. Extra Work 339,026.40 -5,579.50 b. Adustment Comp. -7,520.00 0.00 3. Materials on Hand 0.00 -5,280.00 4. Earned Subject to Retention 2,889,576.30 209,399.20 5. Mobilization 439,000.00 0.00 6. Total Work Completed 3,328,576.30 7. Deductions -84,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,244,576.30 209,399.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,399.20