Dept. of Trans. PROGRESS Serial No. Contract No. 13-262-14-07 04-4G3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 62% 04-CC-80-10.7/10.7 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-13 FONSECA/ MC ELROY GRINDING CO INC 336 E GISH ROAD SAN JOSE CA 95112 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,931.11 42,931.11 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 42,931.11 42,931.11 5. Mobilization 13,402.50 13,402.50 6. Total Work Completed 56,333.61 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,333.61 56,333.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,333.61