Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-105-08-31 04-4G4004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-13-13.2/13.7 NONE Progress payment No. 008 Payment period ending: 12-17-14 BAY CITIES PAVING & GRADING P O BOX 6227 CONCORD CA 94524 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 537,750.54 22,590.50 2. a. Extra Work 33,853.74 925.94 b. Adustment Comp. 35,620.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 607,225.13 23,516.44 5. Mobilization 6. Total Work Completed 607,225.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 607,225.13 23,516.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,516.44