Dept. of Trans. PROGRESS Serial No. Contract No. 17-264-09-41 04-4G4604 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 100% Location: Federal Project: 04-MRN-101 NHP-Q101(277) Progress payment No. 020 Payment period ending: 09-20-17 GHILOTTI BROS / RM HARRIS JV 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,825,593.81 192,289.55 2. a. Extra Work 483,091.85 76,666.59 b. Adustment Comp. 250,000.00 50,000.00 3. Materials on Hand 95,473.67 -39,979.59 4. Earned Subject to Retention 6,654,159.33 278,976.55 5. Mobilization 717,666.37 0.00 6. Total Work Completed 7,276,352.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,371,825.70 278,976.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,976.55