Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-13-22 04-4G4804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 39% Location: Federal Project: 04-SON-101-33.4/34.8 HSNH-Q101(315) Progress payment No. 008 Payment period ending: 11-20-18 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 762,897.15 0.00 2. a. Extra Work 39,367.78 13,852.04 b. Adustment Comp. 47,260.73 -2,542.00 3. Materials on Hand 4. Earned Subject to Retention 849,525.66 11,310.04 5. Mobilization 88,000.00 0.00 6. Total Work Completed 937,525.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 937,525.66 11,310.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,310.04