Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-16-12 04-4G5104 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 10% Location: Federal Project: 04-SOL-80-31.3/32.9 ACIM-080-2(368) Progress payment No. 001 Payment period ending: 06-20-17 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 321,087.05 321,087.05 2. a. Extra Work 4,407.66 4,407.66 b. Adustment Comp. 3. Materials on Hand 188,843.91 188,843.91 4. Earned Subject to Retention 514,338.62 514,338.62 5. Mobilization 413,263.84 413,263.84 6. Total Work Completed 738,758.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 927,602.46 927,602.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 927,602.46