Dept. of Trans. PROGRESS Serial No. Contract No. 17-139-14-43 04-4G5524 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 44% Location: Federal Project: 04-SOL-29-0.8/3.0 HSNH-PP02-9(124) Progress payment No. 003 Payment period ending: 05-20-17 ST FRANCIS ELECTRIC INC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 235,011.75 155,758.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 110,732.16 0.00 4. Earned Subject to Retention 345,743.91 155,758.40 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 330,011.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 440,743.91 175,758.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 175,758.40