Dept. of Trans. PROGRESS Serial No. Contract No. 17-201-18-00 04-4G5524 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 95% Location: Federal Project: 04-SOL-29-0.8/3.0 HSNH-PP02-9(124) Progress payment No. 005 Payment period ending: 07-20-17 ST FRANCIS ELECTRIC INC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 685,135.25 133,667.05 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 685,135.25 133,667.05 5. Mobilization 100,000.00 0.00 6. Total Work Completed 785,135.25 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -13,366.71 -13,366.71 c. Reduction after 95% Comp. 9. Total pay to Contractor 761,768.54 110,300.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 110,300.34