Dept. of Trans. PROGRESS Serial No. Contract No. 15-321-10-41 04-4G5914 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 5% Location: Federal Project: 04-SM-280-9.4 NONE Progress payment No. 003 Payment period ending: 11-20-15 RGW CONSTRUCTION, INC. 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,216.00 186,003.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 626,216.00 186,003.50 5. Mobilization 74,000.00 0.00 6. Total Work Completed 700,216.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 700,216.00 186,003.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,003.50