Dept. of Trans. PROGRESS Serial No. Contract No. 19-259-13-37 04-4G5914 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 91% Location: Federal Project: 04-SM-280-9.4 NONE Progress payment No. 049 Payment period ending: 09-20-19 RGW CONSTRUCTION INC 6267 SOUTHFRONT RD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 691,292.00 550.00 2. a. Extra Work 10,050.69 0.00 b. Adustment Comp. 34,958.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 736,300.69 550.00 5. Mobilization 74,000.00 0.00 6. Total Work Completed 810,300.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 810,300.69 550.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 550.00