Dept. of Trans. PROGRESS Serial No. Contract No. 15-292-14-59 04-4G6304 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 33% Location: Federal Project: 04-SM-280-R25.5 NONE Progress payment No. 001 Payment period ending: 10-20-15 TKO GENERAL ENGINEERING AND CONSTRUCTION INC PO BOX 620698 WOODSIDE CA 94062 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,783.59 49,783.59 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 49,783.59 49,783.59 5. Mobilization 6. Total Work Completed 49,783.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,783.59 49,783.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,783.59