Dept. of Trans. PROGRESS Serial No. Contract No. 16-111-15-34 04-4G6404 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 3% Location: Federal Project: 04-SM-84-21.6 NHP-P084(44) Progress payment No. 003 Payment period ending: 04-20-16 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 209,049.65 194,049.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 282,154.02 41,655.00 4. Earned Subject to Retention 491,203.67 235,704.65 5. Mobilization 243,750.00 81,250.00 6. Total Work Completed 452,799.65 7. Deductions 0.00 162,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 734,953.67 479,454.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 479,454.65