Dept. of Trans. PROGRESS Serial No. Contract No. 18-261-13-26 04-4G6504 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 45% Location: Federal Project: 04-SM-1-4.2/4.2 ACST-P001(629) Progress payment No. 004 Payment period ending: 09-20-18 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 740,256.95 19,065.00 2. a. Extra Work 22,940.21 22,940.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 763,197.16 42,005.21 5. Mobilization 74,636.80 0.00 6. Total Work Completed 837,833.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 837,833.96 42,005.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,005.21