Dept. of Trans. PROGRESS Serial No. Contract No. 22-143-12-15 04-4G8204 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 87% Location: Federal Project: 04-MRN-101-10.6/10.8 B1NH-Q101(343) Progress payment No. 020 Payment period ending: 05-20-22 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,311,876.05 4,200.00 2. a. Extra Work 699,389.77 15,923.16 b. Adustment Comp. 27,000.00 27,000.00 3. Materials on Hand 860,012.41 27,724.96 4. Earned Subject to Retention 9,898,278.23 74,848.12 5. Mobilization 1,150,000.00 0.00 6. Total Work Completed 10,188,265.82 7. Deductions -1,330.41 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,046,947.82 74,848.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,848.12