Dept. of Trans. PROGRESS Serial No. Contract No. 23-109-11-45 04-4G84A4 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 3% Location: Federal Project: 04-NAP-128-20.1/20.4 NONE Progress payment No. 002 Payment period ending: 04-20-23 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,137.76 9,652.76 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 19,137.76 9,652.76 5. Mobilization 22,250.00 22,250.00 6. Total Work Completed 41,387.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,387.76 31,902.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,902.76