Dept. of Trans. PROGRESS Serial No. Contract No. 19-168-11-36 04-4G8804 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 22% Location: Federal Project: 04-ALA-880-10.7/10.7 B1IM-880-1(83) Progress payment No. 002 Payment period ending: 06-20-19 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,226.54 301,691.59 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 12,950.25 12,950.25 4. Earned Subject to Retention 362,176.79 314,641.84 5. Mobilization 255,000.00 255,000.00 6. Total Work Completed 604,226.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 617,176.79 569,641.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 569,641.84