Dept. of Trans. PROGRESS Serial No. Contract No. 19-051-15-50 04-4G8904 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 24% Location: Federal Project: 04-CC-580-5.8/5.8 ACIM-580-1(75) Progress payment No. 005 Payment period ending: 02-20-19 BROSAMER & WALL INC 1777 OAKLAND BLVD # #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 304,925.00 42,950.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 322,336.49 193,936.49 4. Earned Subject to Retention 627,261.49 236,886.49 5. Mobilization 495,000.00 165,000.00 6. Total Work Completed 799,925.00 7. Deductions -40,000.00 -40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,082,261.49 361,886.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,886.49