Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-15-57 04-4G8904 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 60% Location: Federal Project: 04-CC-580-5.8/5.8 ACIM-580-1(75) Progress payment No. 011 Payment period ending: 08-20-19 BROSAMER & WALL INC 1777 OAKLAND BLVD # #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 749,165.00 91,800.00 2. a. Extra Work 19,968.85 0.00 b. Adustment Comp. 3. Materials on Hand 933,717.80 18,725.93 4. Earned Subject to Retention 1,702,851.65 110,525.93 5. Mobilization 627,000.00 0.00 6. Total Work Completed 1,396,133.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,329,851.65 110,525.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 110,525.93