Dept. of Trans. PROGRESS Serial No. Contract No. 21-048-09-36 04-4G8924 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 61% Location: Federal Project: 04-CC-580-5.6/6.2 NONE Progress payment No. 004 Payment period ending: 02-20-21 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 690,314.97 70,692.07 2. a. Extra Work 105,871.22 105,871.22 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 796,186.19 176,563.29 5. Mobilization 74,272.75 0.00 6. Total Work Completed 870,458.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 870,458.94 176,563.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,563.29