Dept. of Trans. PROGRESS Serial No. Contract No. 18-052-09-06 04-4G9904 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 68% Location: Federal Project: 04-SCL-85-2.0/4.6 ACNH-P085(60) Progress payment No. 005 Payment period ending: 02-20-18 GRANITE ROCK COMPANY 5225 HELLYER AVE, #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,534,905.20 0.00 2. a. Extra Work 26,309.57 26,309.57 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,561,214.77 26,309.57 5. Mobilization 183,550.00 0.00 6. Total Work Completed 1,744,764.77 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,744,764.77 36,309.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,309.57