Dept. of Trans. PROGRESS Serial No. Contract No. 19-351-14-21 04-4H0804 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 49% Location: Federal Project: 04-ALA-238-R14.5/R14.5 B1IM-X001(650) Progress payment No. 007 Payment period ending: 12-20-19 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 551,521.17 119,217.25 2. a. Extra Work 70,038.46 8,078.44 b. Adustment Comp. 3. Materials on Hand 8,831.11 8,831.11 4. Earned Subject to Retention 630,390.74 136,126.80 5. Mobilization 210,900.00 0.00 6. Total Work Completed 832,459.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 841,290.74 136,126.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,126.80