Dept. of Trans. PROGRESS Serial No. Contract No. 18-264-14-15 04-4H2004 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 86% Location: Federal Project: 04-NAP-29-13.5/25.5 CNHP-P029(134) Progress payment No. 007 Payment period ending: 09-20-18 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,052,672.42 2,844,278.28 2. a. Extra Work 209,054.05 60,205.17 b. Adustment Comp. 190,494.24 186,294.24 3. Materials on Hand 4. Earned Subject to Retention 12,452,220.71 3,090,777.69 5. Mobilization 1,370,000.00 0.00 6. Total Work Completed 13,822,220.71 7. Deductions -13,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,808,720.71 3,090,777.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,090,777.69