Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-12-31 04-4H2104 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 70% Location: Federal Project: 04-SM-1-40.4/R48.0 ACNH-P001(630) Progress payment No. 006 Payment period ending: 10-20-18 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,271,342.62 512,672.48 2. a. Extra Work 41,427.02 3,100.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,312,769.64 515,772.48 5. Mobilization 160,000.00 0.00 6. Total Work Completed 10,472,769.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,472,769.64 515,772.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 515,772.48