Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-15-58 04-4H2104 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 92% Location: Federal Project: 04-SM-1-40.4/R48.0 ACNH-P001(630) Progress payment No. 011 Payment period ending: 03-20-19 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,863,885.92 268,198.10 2. a. Extra Work 941,747.81 4,444.28 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,805,633.73 272,642.38 5. Mobilization 160,000.00 0.00 6. Total Work Completed 12,965,633.73 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,955,633.73 272,642.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 272,642.38