Dept. of Trans. PROGRESS Serial No. Contract No. 15-202-06-47 04-4H2214 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 55% Location: Federal Project: 04-ALA-580-R41.2/47.0 NHPI-X001(588) 04-ALA-80-2.1/3.0 Progress payment No. 003 Payment period ending: 07-20-15 O.C. JONES & SONS, INC. 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,523,570.33 1,460,998.91 2. a. Extra Work 53,875.10 53,875.10 b. Adustment Comp. 3. Materials on Hand 205,307.90 0.00 4. Earned Subject to Retention 3,782,753.33 1,514,874.01 5. Mobilization 956,650.00 201,400.00 6. Total Work Completed 4,534,095.43 7. Deductions -55,109.00 -46,200.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,684,294.33 1,670,074.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,670,074.01