Dept. of Trans. PROGRESS Serial No. Contract No. 17-111-15-35 04-4H2224 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 23% Location: Federal Project: 04-ALA-580-R41.4/46.1 NHP-X001(602) 04-ALA-24-R2.0 Progress payment No. 002 Payment period ending: 04-20-17 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 425,065.00 239,014.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 425,065.00 239,014.00 5. Mobilization 236,250.00 78,750.00 6. Total Work Completed 661,315.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 661,315.00 317,764.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 317,764.00