Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-10-35 04-4H2604 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 18% Location: Federal Project: 04-ALA-580-41.4 NONE Progress payment No. 004 Payment period ending: 02-20-17 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE CT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 855,254.50 200,060.23 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 855,254.50 200,060.23 5. Mobilization 45,700.00 2,285.00 6. Total Work Completed 900,954.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 900,954.50 202,345.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,345.23