Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-12-12 04-4H5804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 53% Location: Federal Project: 04-ALA-880-11.8/27.5 ACIM-8801(81) Progress payment No. 018 Payment period ending: 08-20-19 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,406,144.26 3,046,538.49 2. a. Extra Work 696,640.55 117,674.85 b. Adustment Comp. 43,824.24 0.00 3. Materials on Hand 164,301.00 0.00 4. Earned Subject to Retention 33,310,910.05 3,164,213.34 5. Mobilization 3,755,000.00 0.00 6. Total Work Completed 36,901,609.05 7. Deductions -17,020.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,048,890.05 3,164,213.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,164,213.34