Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-16-19 04-4H5804 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 62% Location: Federal Project: 04-ALA-880-11.8/27.5 ACIM-8801(81) Progress payment No. 020 Payment period ending: 10-20-19 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,857,152.15 1,171,720.33 2. a. Extra Work 847,957.83 107,396.65 b. Adustment Comp. 622,241.57 510,167.33 3. Materials on Hand 142,289.00 -22,012.00 4. Earned Subject to Retention 38,469,640.55 1,767,272.31 5. Mobilization 3,755,000.00 0.00 6. Total Work Completed 42,082,351.55 7. Deductions -17,020.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 42,207,620.55 1,767,272.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,767,272.31