Dept. of Trans. PROGRESS Serial No. Contract No. 19-079-14-34 04-4H7514 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 33% Location: Federal Project: 04-SF-82-0.0/0.1 HSST-000C(460) 04-SCL-82-10.2/26.3 04-SCL-130-2.3/2.6 Progress payment No. 004 Payment period ending: 03-20-19 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,124.75 383,600.00 2. a. Extra Work 27,038.29 27,038.29 b. Adustment Comp. 3. Materials on Hand 364,645.34 329,788.76 4. Earned Subject to Retention 876,808.38 740,427.05 5. Mobilization 349,600.00 349,600.00 6. Total Work Completed 861,763.04 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,216,408.38 1,080,027.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,080,027.05