Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-08-21 04-4H7514 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 91% Location: Federal Project: 04-SF-82-0.0/0.1 HSST-000C(460) 04-SCL-82-10.2/26.3 04-SCL-130-2.3/2.6 Progress payment No. 011 Payment period ending: 10-20-19 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,580,959.44 42,380.04 2. a. Extra Work 241,634.80 26,043.95 b. Adustment Comp. 92,707.31 0.00 3. Materials on Hand 14,382.55 0.00 4. Earned Subject to Retention 2,929,684.10 68,423.99 5. Mobilization 368,000.00 0.00 6. Total Work Completed 3,283,301.55 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,277,684.10 68,423.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,423.99