Dept. of Trans. PROGRESS Serial No. Contract No. 16-168-12-50 04-4H8304 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 41% Location: Federal Project: 04-ALA-24-0.0 BHNH-P XOO1-603(E) Progress payment No. 003 Payment period ending: 06-20-16 WESTERN STRUCTURES 6005 TYLER ST RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 344,534.94 173,122.12 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 344,534.94 173,122.12 5. Mobilization 211,447.22 70,482.41 6. Total Work Completed 555,982.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 555,982.16 243,604.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,604.53