Dept. of Trans. PROGRESS Serial No. Contract No. 18-163-13-34 04-4H8804 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 04-SCL-280-15.0/15.0 HSIM-280-1(147) Progress payment No. 010 Payment period ending: 06-20-18 GRANITE ROCK COMPANY 5225 HELLYER AVE, #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 694,928.70 747.00 2. a. Extra Work 128,982.82 5,608.49 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 823,911.52 6,355.49 5. Mobilization 83,000.00 0.00 6. Total Work Completed 906,911.52 7. Deductions -2,584.54 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 904,326.98 6,355.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,355.49