Dept. of Trans. FINAL Serial No. Contract No. 17-009-11-28 04-4J0104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SON-101-42.3/42.3 NONE Progress payment No. 008 Payment period ending: 06-24-16 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,480.00 0.00 2. a. Extra Work 688,854.15 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 695,334.15 0.00 5. Mobilization 6. Total Work Completed 695,334.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 695,334.15 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00