Dept. of Trans. PROGRESS Serial No. Contract No. 21-140-07-43 04-4J0804 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 95% Location: Federal Project: 04-SM-280-R20.2/R20.6 STER-27F4(1) Progress payment No. 002 Payment period ending: 05-20-21 AMERICA PACIFIC CONSTRUCTION 7161 CITRUS VALLEY AVENUE EASTVALE CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 426,818.60 275,688.60 2. a. Extra Work 24,415.99 24,415.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,234.59 300,104.59 5. Mobilization 35,000.00 1,750.00 6. Total Work Completed 486,234.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 486,234.59 301,854.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 301,854.59